Project Location: Suzhou Industrial Park, Jiangsu Province, China
Project Overview

The Science and Technology Park factory building project in Suzhou Industrial Park required a large-scale scaffolding solution for exterior wall construction, roof installation, and equipment mounting. Given the project’s scale and the need for both speed and safety, a ringlock scaffold system was deployed as the primary access platform.
Industry: Industrial Construction
Location: Suzhou, Jiangsu Province
Scope: Exterior facade scaffolding, roof installation support, and interior access towers
Project Requirements
High load-bearing capacity to support heavy construction materials.
Quick installation using modular ringlock scaffolding parts.
Safe working platforms with durable scaffold planks.
Adaptable scaffolding tower structures for multi-level factory construction.
Corrosion-resistant steel suitable for long project duration.

Our Solution
Zhuozhan Industrial provided a customized steel ringlock scaffolding system:
Scaffold tubes and ledgers formed the main framework with strong load capacity.
Anti-slip steel scaffold planks provided safe access for workers.
Scaffolding ladders integrated for easy vertical movement.
Scaffolding accessories and clamps ensured secure connections.
Modular scaffolding tower systems adapted to both interior and exterior construction needs.
Execution Process
Planning & Design – Engineers developed a layout to cover both facade and roof construction areas.
Assembly – The ringlock scaffolding components were installed quickly, minimizing disruption to parallel construction works.
On-site Use – Workers safely conducted facade installation, roof truss mounting, and interior mechanical setups.
Dismantling – After project completion, the ringlock scaffolding set was dismantled and prepared for reuse.
Outcome & Benefits
Safety: The ringlock scaffold system provided stability during high-altitude operations.
Efficiency: Quick installation reduced project timeframes in the busy Suzhou Industrial Park.
Durability: Steel ringlock scaffolding with galvanized finish resisted wear during long-term use.
Flexibility: Modular scaffolding adapted to different factory sections, from exterior walls to high roof spans.
Client Feedback
“The ringlock scaffolding system provided the reliability we needed for a high-tech industrial project. It supported our construction schedule while maintaining excellent safety standards.”
— Project Manager, Suzhou Science & Technology Park